Alpha Torbanite Project Update
Released
Released
Announcement PDF
23 October 2023
ALPHA PROJECT UPDATE – LIQUEFACTION TEST
PROGRAM FOUR GATHERS MOMENTUM, PAVING WAY
FOR PFS COMPLETION
Key first steps completed in Test Program Four; Resource upgrade due in early November
following completion of extensive Phase 2 drill campaign.
Key Points:
•
Strong progress being achieved with Test Program Four at Monash University.
•
2/3 Licella supercritical water test runs now complete, with samples under
assessment by Petrolab.
•
Monash test runs underway with first samples produced utilising Alpha core.
•
Technix due to commence identification of bituminous product samples as first
bulk samples are sent for assessment.
•
SRK Consultants undertaking resource modelling – resource upgrade
scheduled for delivery in early November, with expected upside in the size of
the resource.
Greenvale Energy Limited (ASX: GRV, “Greenvale” or “the Company”) is pleased to provide
an update on ongoing testwork and development activities for its flagship 100%-owned Alpha
Torbanite Project in central Queensland.
Greenvale CEO, Mark Turner, said:
“While we have recently expanded our portfolio with the exciting acquisition of a high-grade
helium and hydrogen project in central Australia that we believe will add significant value to
the Company and the Alpha Project unequivocally remains our priority and flagship asset.
“I am energised by the recent progress we have achieved, and I am confidently looking forward
to the completion of Test Program Four and the forthcoming release of the long-awaited Pre
Feasibility Study (PFS)”.
“This will mark a crucial milestone in the commercialisation of Alpha and a significant step
towards the Company achieving its goal of becoming the only domestic, end-to-end producer
of sustainable bituminous products to feed the critical infrastructure needs of Australia.”
As outlined in Greenvale’s market announcement dated 23 August 2023, Liquefaction Test
Program Four is now well underway and proceeding on schedule. The program comprises of
REGISTERED OFFICE:
Level 5, Suite 6 189 Kent Street, Sydney, New South Wales 2000 | GPO Box 2733, Sydney NSW 2001
+61 2 8046 2799 | admin@greenvaleenergy.com.au | www.greenvaleenergy.com.au
ABN
54
000
743
555
three distinct assessments run by Monash University (Monash), Licella Holdings Ltd (‘Licella’)
and Technix (see Figure 1).
Figure 1: Greenvale's Liquefaction Test Program Flow Chart
Licella has been engaged to undertake a Scoping Study at batch level to better define the
yield and structure of products, under PROCOM direction, utilising variations of supercritical
water processing conditions that could potentially simplify the processing of the Alpha
Torbanite Deposit.
As announced on 2 October 2023, Licella has completed the first supercritical water test run
and the samples from the reaction tests have been sent to Petrolab for analysis. Petrolab’s
work is ongoing but it is expected that the initial results from the first test run will be provided
imminently. Licella has now also performed the second of its three slated tests runs with
samples being prepared for transportation to Petrolab for analysis.
Monash University's ongoing work program involves verifying prior results using core samples,
conducting tests with both oil and supercritical water as carriers, and producing a one-litre bulk
samples for final analysis. They are also performing a full suite of tests on the 16 original core
samples, providing periodic updates to Greenvale, and will deliver comprehensive reports
upon completion. This extensive program, currently in progress, builds on positive results from
earlier tests, establishing a processing pathway crucial for the Alpha Project and the eventual
Pre-Feasibility Study (PFS).
Monash has completed calibration of their PARR reactor, which has undergone its first test
run, creating their first sample using cannelite only. Subsequent analysis of this sample has
been performed internally by Monash, with results communicated to Greenvale’s technical
consultants, PROCOM. The results of this initial test run will be communicated in due course,
as future test runs are completed providing further validity and context. At the time of this
GREENVALE
ENERGY
LIMITED
2
release, Monash is about to commence test run two, out of a total planned sixteen runs. As
previously stated, the results of this test run will be communicated in due course.
Calibration of the Parr Reactor equipment is a crucial step in the liquefaction test procedure
and ensures that future testing will be completed in a timely manner.
PROCOM have continued their diligent work and have produced the first bulk samples (fivelitres) for independent assessment by Technix, Greenvale’s bituminous product advisor. The
bulk sample is currently in transit to New Zealand, with Technix’s findings to be relayed to the
Company’s technical team as they are made available. It is not anticipated that this first sample
will produce the final decided product suite; instead it is hoped that it will be used by Technix
to better understand the unique properties of the Alpha Deposit.
Simultaneously, the Company expects that the results from the recently completed Alpha
Phase 2 drilling will also be made available in the coming weeks (early November).
As previously reported on 2 October 2023, the Company completed the Phase 2 drilling
program at the Alpha Project with initial results expected to increase both the size and
confidence of the current 18.6Mt Mineral Resource. The core drilling programme comprised a
total of 20 HQ core holes for a combined 1,053.5m of drilling.
The program involved the acquisition of 16 cores targeting the Upper & Lower Seams and four
cores targeting just the Lower Seam. All core hole locations have been geophysically logged
with wireline tools providing down-hole gamma, density and verticality surveys. Detailed
logging of the core is now complete, with assays nearing completion.
Respected mining consultants, SRK Consulting, are completing the updated resource
modelling. Management is confident that the resulting resource estimate will further enhance
the potential commercial viability of the Alpha Project.
With regard to upcoming work programs, the Company’s development plan involves
conducting further tests using the PROCOM Parr Reactor, using a blend of Torbanite and
cannelite to produce more bulk samples. This is intended to build on current progress and
assist Technix with their analysis at their New Zealand bitumen lab. Additionally, once data
from Test Program 4 (Monash & Licella) becomes available, the simulation work to estimate
emissions and overall balances will continue. This is crucial as it relies on yield and quality
assumptions, and the figures will be released once test results are obtained.
AUTHORISED FOR RELEASE:
The Board of Greenvale has approved this announcement for release.
FOR FURTHER DETAILS, CONTACT:
Mark Turner, CEO, 0459 519 999
MEDIA INQUIRIES:
Nicholas Read
Read Corporate
Nicholas@readcorporate.com.au
Mobile: 0419 929 046
GREENVALE
ENERGY
LIMITED
3
FUTURE STATEMENTS
Statements contained in this release are or may be forward looking statements. Such
statements relate to future events and expectations and as such involve known and unknown
risks and significant uncertainties, many of which are outside the control of Greenvale. Actual
results, performance, actions and developments of Greenvale Energy may differ materially
from those expressed or implied by the forward-looking statements in this release. Such
forward looking statements speak only as of the date of this release. There can be no
assurance that actual outcomes will not differ materially from these statements. A number of
important factors could cause actual results or performance to differ materially from the
forward-looking statements. Investors should consider the forward-looking statements
contained in this release in light of those disclosures. To the maximum extent permitted by law
(including the ASX Listing Rules), Greenvale and any of its affiliates and their directors,
officers, employees, agents, associates and advisers disclaim any obligations or undertaking
to release any updates or revisions to the information in this release to reflect any change in
expectations or assumptions; do not make any representation or warranty, express or implied,
as to the accuracy, reliability or completeness of the information in this document, or likelihood
of fulfilment of any forward-looking statement or any event or results expressed or implied in
any forward-looking statement; and disclaim all responsibility and liability for these forwardlooking statements (including, without limitation, liability for negligence). Nothing in this
document will under any circumstances create an implication that there has been no change
in the affairs of Greenvale since the date of this release.