Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
29 January 2025
DECEMBER 2024 QUARTERLY REPORT
URANIUM PORTFOLIO EXPANDED WITH NEW PROJECT
ACQUISITIONS; AIRBORNE SURVEY DEFINES EXTENSIVE URANIUM
ANOMALISM; ALPHA TEST PROGRAM 5 DELIVERS POSITIVE RESULTS
Highlights
Multiple Uranium Projects, NT
• Binding Heads of Agreement (HoA) to acquire an initial 80% interest in the following
Uranium Projects
o Henbury Uranium Project, 120km south-west of Alice Springs in the Amadeus Basin
of the NT.
o Tobermorey Uranium Project, 400km east-north-east of Alice Springs in the Eastern
Arunta Mineral Field
o Elkedra Uranium Project, 300km north-east of Alice Springs,
• 3,588 line-kilometre airborne magnetics/radiometrics survey flown over the Henbury
project area at 100m spacing:
o 10km long arcuate uranium anomaly identified within ferricrete overlying the
Pacoota Sandstone within EL33637.
o Additional 2km long uranium anomaly confirmed within EL33637.
o Uranium anomaly adjacent to thrust faulted Pacoota Sandstone within EL33638.
• 9,879 line kilometre airborne magnetics/radiometrics survey flown over the Tobermorey
project area at 100m spacing, with extensive uranium anomalism confirmed along a 20km
strike length and 15km width at its widest point.
Oasis Uranium Project, Qld
• Acquisition of 100% interest in the advanced high-grade Oasis Uranium Project, 50km west
of Greenvale FNQ, covering 90km2 of fault bound alkaline intrusive and metamorphic
terrane which includes the high grade Oasis uranium deposit and 8 additional high priority
uranium targets.
Alpha Torbanite Project, QLD (100%-owned):
• Liquefaction Test Program 5 successfully completed by The University of Jordan (UofJ).
• Test Program 5 was aimed at improving the viscosity of the final bitumen product to
determine the potential to deliver a premium-grade C170 product from the Alpha Project.
• Results indicate that, with further fine-tuning of experimental parameters, a viscosity in the
range of C170 asphalt could be achieved with Alpha ore.
• Test Program 6 commenced subsequent to the end of the Quarter.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Corporate:
• Highly experienced mining executive Neil Biddle appointed Executive Chairman, with Mark
Turner stepping down as Director and CEO at the end of the Quarter. Mark will remain with
Greenvale as an Independent Contractor.
• Agreement reached to divest the Company’s stake in the EP145 project to Mosman Oil &
Gas in exchange for full reimbursement of the acquisition costs incurred by Company to
date. The sale proceeds of $250,000 were received subsequent to the end of the Quarter.
• $1.176 million in R&D rebates received for the 2024 Financial Year.
Projects
NT Uranium Projects
Greenvale further strengthened its portfolio of high-potential Australian uranium exploration
projects in the Northern Territory during the Quarter, with the acquisition of the Henbury
Project, a highly prospective calcrete-hosted uranium project in the Amadeus Basin region; the
Tobermorey Project, a new highly prospective sandstone-hosted uranium project located in
the eastern Arunta region; and the Elkedra Project, which sits within Cambrian Georgina Basin
metasediments in the NT and is prospective for sandstone-hosted and unconformity style
uranium deposits.
Greenvale secured the rights to obtain an immediate 80% interest in the three Uranium
Projects with the original project owners, Gempart (NT) Pty Ltd, being free-carried through to
a Definitive Feasibility Study (DFS). Greenvale has incurred a small upfront cost of
approximately $30,000 ($10,000 per project) payable to Gempart as reimbursement of data
acquisition costs to secure its 80% interest in the projects.
Following the acquisition of the Douglas River Uranium Project during the September 2024
Quarter, Greenvale now holds four uranium exploration projects in the NT, establishing an
exciting exploration pipeline of projects and prospects to be tested in the months ahead.
Further information can be found in the following announcements:
•
16th Sept - Greenvale acquires Tobermorey Uranium Project in the NT
•
21st Sept - Greenvale acquires Prospective Henbury Uranium Project
•
20th Nov - Greenvale adds fourth highly prospective NT uranium project
•
19th Nov - Uranium anomalism confirmed by airbourne surveys in the NT
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Figure 1: Location – NT Uranium Projects
Henbury Uranium Project
Greenvale completed 3,588 line-kilometres of in-fill airborne magnetics/radiometrics survey
over the Henbury Project during the Quarter, flown at 100m spacing. This survey defined
several key targets including:
•
•
•
10km long arcuate uranium anomaly identified within ferricrete overlying the Pacoota
Sandstone within EL33637.
Additional 2km long uranium anomaly confirmed within EL33637.
Uranium anomaly adjacent to thrust faulted Pacoota Sandstone within EL33638.
The complete dataset is now being modelled by Montana GIS and detailed interpretation of
magnetics overlain by radiometrics.
Tobermorey Uranium Project
Historically a 400m line spaced airborne magnetics/radiometric survey completed by the NTGS
(in 1999) has defined multiple U and U/Th ratio anomalies which are concentrated within
extensive paleochannels hosted by Tertiary limestone. The largest uranium anomaly is over
EL33621 trending east-south-east for 20km, 15km at its widest point, straddling the Plenty
Highway about 10km from the NT-QLD border. Other Cenozoic basins and palaeodrainages
in Central and Southern NT are currently being explored for uranium. Many parallels can be
drawn between Tobermorey and the calcrete-hosted uranium occurrences within and south of
the Ngalia Basin including Napperby, Currinya and Cappers.
Greenvale completed 9,879 line-kilometres of in-fill airborne magnetics/radiometrics survey
over the Tobermorey Project during the Quarter, flown at 100m spacing. This survey has
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
further defined extensive uranium anomalism along a 20km strike length and 15km width at its
widest point.
The complete dataset is now being modelled by Montana GIS and detailed interpretation of
magnetics overlain by radiometrics.
Douglas River Uranium Project
The Douglas River Project, which was acquired in the September 2024 Quarter, is located
about 200km south of Darwin in the Daly Basin on the south-western side of the Pine Creek
Mineral Field. The project area has been historically explored for numerous minerals including
uranium, gold, tin, base metals, REE’s and diamonds with extensive anomalism defined from
surface sampling.
Greenvale completed 1,044 line-kilometres of in-fill airborne magnetics/radiometrics survey
over the Douglas River Project during the Quarter, flown at 100m spacing. This survey defined
a 13km long uranium anomaly overlying a palaeochannel interpreted from airborne EM, in turn
overlying a geological unconformity.
The western portion of the Douglas River Project could not be flown this year due to station
mustering activities, and the survey has been rescheduled for after the wet season, most likely
in April 2025.
The complete dataset is now being modelled by Montana GIS and detailed interpretation of
magnetics overlain by radiometrics.
Elkedra Uranium Project
The Elkedra Project area occupies an area of 566km in the Barkly region of the Northern
Territory. The region has a semi-arid, tropical climate with average rainfall of 350mm during
the summer period from November to March. The exploration field season traditionally occurs
from late March to mid-November.
A 400m line spaced airborne magnetics/radiometric survey completed by the NTGS (in 1999)
has defined multiple uranium and Uranium/Thorium ratio anomalies which extend continuously
over a strike length of approximately 8km.
Oasis Uranium Project, Queensland
Subsequent to the end of the Quarter, Greenvale acquired a 100% interest in the advanced,
high-grade Oasis Uranium Project.
The Oasis deposit and associated regional uranium anomalism are contained within EPM
27565 which covers 53 sub-blocks over an area of 90km2. The project is located 250km west
of Townsville and 50km west of Greenvale’s assets in Far North Queensland (Figure 13). The
project area is located entirely within the Lynd Station pastoral land.
The Company acquired the 100% interest from the vendors Maverick Exploration Pty Ltd,
Remlain Pty Ltd and Mineral Intelligence Pty Ltd (equal 1/3 each interest) for a consideration
of $200,000 cash and the issue of 20 million Greenvale shares.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Figure 2: Location – Oasis Project
The acquisition of Oasis adds considerable weight to Greenvale’s portfolio of Uranium
exploration projects and is expected to be rapidly upgraded to resource status during the 2025
exploration season.
EPM 27565 covers 90km2 of fault-bound alkaline intrusive and metamorphic terrane, which
includes the high-grade Oasis uranium deposit and eight additional high-priority uranium
targets.
Airborne radiometric uranium anomalies were first located by Anglo American in 1973, with
Esso completing major on-ground work between 1977 and 1979, drilling 46 holes (32 diamond,
14 percussion) for a total of 4,755m. Esso defined high-grade primary uranium mineralisation
over a 300m strike length and 200m vertical depth. The mineralisation remains open at depth
and possibly along strike. Four due diligence diamond drill holes completed in 2006 by
Glengarry Resources validated the historical Esso data and confirmed continuous high-grade
mineralisation with intercepts up to 1m @ 0.72% U3O8 (15.8 lbs/t).
Most recently, Terra Search Pty Ltd reprocessed and interpreted the historical geophysical
data, identifying nine priority uranium anomalies over a 10km strike length adjacent to, and
apparently emanating from, the major terrane boundary delineated as the Lynd Mylonite Zone.
Greenvale proposes an aggressive 2025 exploration program at Oasis, with the goal of
bringing known and extended mineralisation at Oasis to JORC 2012 resource status. This is
to be done in three stages:
1. Geochemical testing of entire Oasis shear which extends under cover for 1.5km north
of identified mineralisation by track etch technique (radon gas cupping, emanometry)
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 5
and geological prospecting.
2. Geochemical testing of eight priority coincident radiometric/structural anomalies by
track etch technique in conjunction with geological prospecting and follow up drilling of
identified targets.
3. Ground truthing and detailed mapping of all undercover structural splays emanating
from the Lynd Mylonite zone where radiometrics don’t work and geochemical testing of
identified splays with track etch technique.
Alpha Project, Queensland
During the Quarter, Greenvale reported results from liquefaction Testwork Program 5 on
samples from the Alpha Project.
Liquefaction Test Program 5 was undertaken by the University of Jordan (UofJ), a world-class
institution with significant expertise in geotechnical/chemical engineering, liquefaction studies
and bituminous products.
Test Program 5 was designed to examine the issues raised in Test Program 4 (see ASX
Announcement 26 June 2024), which found that, while the shale extract from Alpha could be
used for manufacturing standard or modified types of bitumen, it did not meet the stringent
specifications required to deliver a premium C170 bitumen product. The main issues identified
were the viscosity of product and the lack of elasticity.
Subsequent to the end of the Quarter, Greenvale commenced the first stage of Test Program
6. Stage 1 seeks improve the work performed by the UoJ in Test Program 5 and optimise the
processing conditions before Monash University commences the bulk sample test program.
UoJ will conduct the following test runs, from samples already held by UoJ:
1. A long reaction time (5 hours) without a catalyst, at maximum pressure and 370°C.
2. One experiment using THF instead of toluene, also under maximum pressure, at
400°C.
3. Testing catalyzed reactions aimed at maximizing yield and verifying the effect on
viscosity (proposed catalysts: Fe, Sn, Zn, Cu).
It is Greenvale’s expectation that after completing these experiments, the Company would be
in a position to proceed to produce bulk samples under the optimal conditions identified.
Mark Turner, former CEO of Greenvale, will manage the work on behalf of Greenvale as an
Independent Contractor.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 6
Corporate Activities
Board Changes
Greenvale has undertaken a restructure of its Board, with Mark Turner resigning as a Director
and stepping down as Chief Executive Officer on 31 December 2024. Mr Turner has been
retained by Greenvale as an Independent Contactor to keep progressing the Alpha Torbanite
Project as the Company moves into Test Program 6, which will include a bulk testwork
program.
Neil Biddle has taken up the role of Executive Chairman role while the Company moves
through its next stage of development.
Mr Biddle is a highly experienced mining executive and geologist with over 35 years of
professional and management experience in the exploration and mining industry. He was a
founding Director of ASX-100 lithium producer Pilbara Minerals and a key force behind that
company’s early growth and success including the acquisition, drill-out and development of the
Pilgangoora Lithium Project in WA.
In addition to his role as Executive Chair of Greenvale, Mr Biddle is also a non-executive
director ASX-listed gold explorer Trek Metals (ASX: TKM).
Disposal of Interest in EP145
During the Quarter, Greenvale reached an agreement to dispose of its 75% farm-in interest in
the EP145 project to Mosman Oil and Gas Limited (Mosman). Under the terms of the sale
agreement, Greenvale will receive $250,000, which was received subsequent to the end of the
reporting period.
The Company’s decision to divest from the EP145 project aligns with Greenvale's strategic
focus on optimising its portfolio and concentrating resources on its core projects. Notably, the
Company views its recently acquired uranium assets as a significant growth opportunity and
believes that by disposing of its interest in EP145, it can more effectively redirect resources
towards these high-potential opportunities.
Finalisation of Pioneer Agreement
Greenvale has entered into an agreement with Pioneer Resources Partners LLC (Pioneer) for
early termination of the Subscription Agreement announced to the market on 1 February 2023.
Greenvale has agreed to pay Pioneer $2 million in cash and issue 13,144,444 shares at $0.022
per share in relation to the balance outstanding to Pioneer.
ASX Additional Information
The Company provides the following information pursuant to ASX Listing Rule requirements:
1. ASX Listing Rule 5.3.1:
Exploration and Evaluation Expenditure during the Quarter was $79,000. Full details of
exploration activity during the December 2024 Quarter are set out in this report.
Below is the breakdown of the expenditure incurred:
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 7
Table 1 Analysis of exploration expenditure
Property
Nature of expenses
Amount ($)
Alpha Project
Alpha Testwork
72,000
Mining administration and environmental
compliance cost
7,000
Subtotal – Alpha Project
79,000
Total Exploration costs
2.
79,000
ASX Listing Rule 5.3.2:
The Company confirms that there was no mine production and development activities for the
Quarter.
3.
ASX Listing Rule 5.3.5:
Payment to related parties of the Company and their associates during the quarter was
$101,783 in cash.
The Company advises that this relates to remuneration of Directors only. Please see the
Remuneration Report in the Company’s Annual Report for further details on Directors’
Remuneration.
Authorised for Release
This announcement and the accompanying Appendix 5B have been approved by the
Board for release.
Contact
For further details, contact:
Neil Biddle, Executive Chairman,
NBiddle@greenvaleenergy.com.au
Media Inquiries:
Nicholas Read – Read Corporate
Nicholas@readcorporate.com.au
Mobile: 0419 929 046
Tenements
In accordance with Listing Rule 5.3.3, Greenvale provides the following Information concerning
its exploration licences:
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 8
Tenement Details
Alpha Project, Queensland
Tenement
%age Ownership
Owned by
Status
MDL 330
100%
Alpha Resources Pty Ltd
Current to 31 January 2027
EPM 27718
100%
Alpha Resources Pty Ltd
Current to 14 February 2026
Geothermal Project, Queensland
Tenement
%age Ownership
Of Applicant
Applicant
Status
EPG 2023
100%
Greenvale Energy Ltd
Under Application
EPG 2024
100%
Greenvale Energy Ltd
Under Application
EPG 2025
100%
Greenvale Energy Ltd
Under Application
EPG 2029
100%
Greenvale Energy Ltd
Under Application
Helium Project, Northern Territory
Tenement
%age Ownership
Owned by
Status
EP 145
80%
Greenvale Gas Pty Ltd
Current to 21 August 2026
Uranium Project, Northern Territory
Tenement
%age Ownership
Owned by
Status
ELA 33900
80%
Greenvale Utilities Pty Ltd
Under Application
EL 33670
80%
Greenvale Utilities Pty Ltd
Current to 19 May 2030
EL 33756
80%
Greenvale Utilities Pty Ltd
Current to 26 September 2030
EL 33637
80%
Greenvale Utilities Pty Ltd
Current to 14 April 2030
EL 33638
80%
Greenvale Utilities Pty Ltd
Current to 14 April 2030
EL 33621
80%
Greenvale Utilities Pty Ltd
Current to 14 April 2030
EL 33692
80%
Greenvale Utilities Pty Ltd
Current to 11 August 2030
•
Mining tenements acquired during the quarter and their location: Nil.
•
Mining tenements disposed during the quarter and their location: Nil.
•
The beneficial percentage interests held in farm-in or farm-out agreements at the end
of the quarter: At the end of the quarter, the Company holds an exclusive right to
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 9
acquire up to 80% of the legal and beneficial interest in the exploration licence EP145
(owned by Mosman Oil & Gas), located in the Northern Territory. The Company also
holds the exclusive right to acquire up to 80% of the legal and beneficial interest in the
exploration licence’s EL 33900, EL 33670, EL 33756, EL 33637, EL 33638, EL 33621,
EL 33692 (owned by GemPart (NT) Pty Ltd), located in the Northern Territory
•
The beneficial percentage interests in farm-in or farm-out agreements acquired or
disposed of during the quarter: During the quarter, the Company acquired the exclusive
right to acquire up to 80% of the legal and beneficial interest in the exploration licence’s
EL 33900, EL 33670, EL 33756, EL 33637, EL 33638, EL 33621, EL 33692 (owned by
GemPart (NT) Pty Ltd), located in the Northern Territory.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 10
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Greenvale Energy Ltd
Quarter ended (“current quarter”)
ABN
54 000 743 555
31 December 2024
Current quarter
$A’000
Year to date (6
months)
$A’000
(477)
(870)
3
9
-
851
(474)
(10)
(c) property, plant and equipment
(23)
(23)
(d) exploration & evaluation
(79)
(620)
Consolidated statement of cash flows
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
(a) exploration & evaluation
(b) development
(c) production
(d) staff costs
(e) administration and corporate costs
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
1.6
Income taxes paid
1.7
Government grants and tax incentives
1.8
Other (provide details if material)
1.9
Net cash from / (used in) operating activities
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
(b) tenements
(e) investments
(f)
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 11
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date (6
months)
$A’000
5
1,530
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
2.3
Cash flows from loans to other entities
2.4
Dividends received (see note 3)
2.5
Other (provide details if material)
25
25
2.6
Net cash from / (used in) investing activities
(72)
912
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt
securities
3.3
Proceeds from exercise of options
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
3.5
Proceeds from borrowings
3.6
Repayment of borrowings
(2.000)
(2,000)
3.7
Transaction costs related to loans and
borrowings
3.8
Dividends paid
3.9
Other (provide details if material)
3.10
Net cash from / (used in) financing activities
(2,000)
(2,000)
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
2,972
1,524
4.2
Net cash from / (used in) operating activities
(item 1.9 above)
(474)
(10)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(72)
912
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
(2,000)
(2,000)
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 12
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
Current quarter
$A’000
Year to date (12
months)
$A’000
4.5
Effect of movement in exchange rates on cash
held
-
-
4.6
Cash and cash equivalents at end of period
425
425
5.
Reconciliation of cash and cash
equivalents
Current quarter
$A’000
Previous quarter
$A’000
425
2,972
425
2,972
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
5.1
Bank balances
5.2
Call deposits
5.3
Bank overdrafts
5.4
Other (provide details)
5.5
Cash and cash equivalents at end of quarter
(should equal item 4.6 above)
6.
Payments to related parties of the entity and their associates
Current quarter
$A'000
6.1
Aggregate amount of payments to related parties and their associates
included in item 1
102
6.2
Aggregate amount of payments to related parties and their associates
included in item 2
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an explanation
for, such payments.
More information concerning the breakdown of the above payments to directors and their related parties can be
found within the accompanying Quarterly Activities Report.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 13
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
7.1
Loan facilities
7.2
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
3,000
-
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
3,000
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest rate,
maturity date and whether it is secured or unsecured. If any additional financing facilities have
been entered into or are proposed to be entered into after quarter end, include a note
providing details of those facilities as well.
3,000
(a)
Loan facilities – directors
The Company announced on 20 October 2022 that it had received a letter of support from its
directors for $3.00 million. The letter of support is to provide an unsecured loan to the Company,
with the following terms:
•
interest at 12.00% per annum; and
•
to be repaid at the earlier of the next capital raising (including an offer entitlement) or
18 months from when the final drawdown has been made by the Company.
(b) Facility – Pioneer Resources LLC
The Company had a facility with an institutional investor, Pioneer Resources LLC for
$4.320 million (inclusive of a premium paid). This facility was fully drawn at 31 March 2023.
The facility is repayable by way of issue of ordinary shares in the Company, unless Greenvale
otherwise elects to repay the facility in cash. For the purposes of Greenvale’s Appendix 5B, the
proceeds from this facility have been reflected as debt and not equity, as it represents the form
of the proceeds received. However, given that the substance of the of the facility is/will be in
the form equity, it has not been shown as part of the financing facilities under Response 7
above.
On 21 November 2024, the Company finalised the facility with Pioneer through the payment of
$2,000,000 and the issue of 13,144,444 shares.
8.
Estimated cash available for future operating activities
$A’000
8.1
Net cash from / (used in) operating activities (item 1.9)
(474)
8.2
(Payments for exploration & evaluation classified as investing activities)
(item 2.1(d))
(79)
8.3
Total relevant outgoings (item 8.1 + item 8.2)
(554)
8.4
Cash and cash equivalents at quarter end (item 4.6)
425
8.5
Unused finance facilities available at quarter end (item 7.5)
-
8.6
Total available funding (item 8.4 + item 8.5)
425
8.7
Estimated quarters of funding available (item 8.6 divided by item
8.3)
0.8
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”. Otherwise, a
figure for the estimated quarters of funding available must be included in item 8.7.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 14
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: Yes.
In January 2025, the Company received an R&D rebate of $1.175m and proceeds from the
sale of EL145 of $250,000. The adjusted 31 December 2024 cash balance, including these
receivables, is $1.85m, giving 3.3 quarters of cashflow based on relevant outgoings in the
December quarter.
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it believe that they will
be successful?
Answer: The Company continues to monitor its cash position, and will take appropriate steps as
required.
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: Yes, refer 8.8.1
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
Date:
This statement gives a true and fair view of the matters disclosed.
29 January 2025
Authorised by: The Board of Directors of Greenvale Energy Ltd
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An entity that
wishes to disclose additional information over and above the minimum required under the Listing Rules is encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash Flows
apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting standards agreed by
ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the [name of
board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a disclosure committee,
you can insert here: “By the Disclosure Committee”.
5.
If this report has been authorised for rel