Key Milestones Achieved with Alpha Project, Test Program 7
Released
Released
Announcement PDF
ASX Release 16 December 2025
Interactive Investor Hub - Engage directly with the Company through our Investor hub, you can ask questions, review
comments and get direct access to the Company – follow the link greenvaleenergy.com.au/announcements
Greenvale Energy Limited ABN 54000743555 W: greenvaleenergy.com E: admin@greenvaleenergy.com.au
Perth: Level 1, 1 Alvan St, Subiaco, 6008 Brisbane: Suite 5-Level 12, 10 Market St, Brisbane 4000 Page | 1
KEY MILESTONES ACHIEVED WITH ALPHA PROJECT TEST
PROGRAM 7 - BULK SAMPLE PRODUCTION TO COMMENCE
Greenvale Energy Limited ASX: GRV (“Greenvale” or “the Company”) is pleased to advise that
the first two milestones of Test Program 7 (TP7) for its 100%-owned Alpha Torbanite Project in
Queensland have been successfully achieved. TP7 is continuing with the next phase of work
being the production of a bulk sample.
Greenvale CEO Alex Cheeseman said:
“Notwithstanding a number of delays, both Greenvale and our service provider, Monash
University, are pleased to report on the successful achievement of the first two milestones of Test
Program 7. Specialist equipment has been designed, procured, installed, commissioned,
operated and, most importantly, has verified the successful scaling of previous test work
outcomes.
“Scaling is a fundamental technical challenge for any mineral processing program, and the work
completed to date has successfully replicated the positive, repeatable results from previous
programs but with a 40 times scale factor. This is a very encouraging development that puts us in
a strong position as we move ahead with the final key stage of Test Program 7 – which has the
single aim of producing a commercial bitumen product to independent C-170 certification.
“Bulk sample production has commenced in December and will continue into the New Year,
setting the conditions for independent assessment, verification and certification. If we can
achieve that, that will represent a major milestone for the Company and the Alpha Torbanite
Project, providing us with a clear pathway to unlock its significant value for shareholders.”
Highlights
First two milestones of Test Program 7 (TP7) for the Alpha Torbanite
Project successfully completed, confirming optimal operating conditions
for the production of bulk samples.
Milestone 2 has successfully scaled the results of Test Program 6 by a
volumetric factor of 40, demonstrating the ability to repeatedly produce
an asphaltene-based product from Alpha’s torbanite.
Bulk sample production to commence in December 2025, with TP7
program milestones extended into 2026.
TP7 has the single objective of producing a bituminous product that can
be independently certified to C-170 asphalt specification.
Greenvale Energy Limited ASX Release
Page | 2
Key Lessons from TP6 that shaped TP7
As previously announced1
, key findings from Greenvale’s previous test programs had determined
the optimal process controls required to maximise product yields from Alpha’s torbanite.
Specific controls include temperature ramp profile, reaction pressure, temperature cooling
profile, optimal catalysts and optimal carriers.
Test Program 6 identified that the temperature rate must increase from room temperature to a
set maximum of 400o
C at a rate of approximately 10o
C/minute. The target peak temperature of
400o
C should then be held for 1 hour to maximum reaction, with zinc identified as the optimum
catalyst for conversion. These process controls combine to optimise the yield of an asphaltene-
heavy product that is produced from torbanite.
Reactions occur in a pressure vessel (autoclave) with peak pressure of 29 Mpa. Reactions also
occur in an oxygen-free environment, achieved through a gas purge followed by hydrogen
pressurisation.
Successful Scaling
The operating conditions are custom requirements, and while aspects of the process are
replicated in other industries, the combination of rapid heating in a very-high pressure and
oxygen-free environment is unique. Greenvale’s service provider (Monash University) was
required to procure bespoke, specialist equipment to enable TP7 to progress.
While delays were encountered in the procurement process, all of the required equipment has
now been procured, installed and operated as designed, as shown in Figure 1.
Figure 1 – Custom heating, cooling and control systems procured for TP7.
TP6 was conducted using pressure vessels capable of containing 100ml of total material. TP7
has replicated the technical controls and operating parameters of TP6 using a pressure vessel of
4 litres, a 40-times volumetric increase in scale from TP6.
1
Refer to ASX Announcement TP6 delivers positive results with highest product conversion to date and the introduction of
catalysts improving viscosity of the final product released 8 April 2025
Greenvale Energy Limited ASX Release
Page | 3
Figure 2 demonstrates the operating profile of the final test run for Milestone 2, setting the
conditions for bulk sample production. Temperature ramp, reaction pressure, maximum
temperature control and temperature cooling are key process controls that were achieved.
Figure 2 – Temperature ramp profile and 1 hour of reaction time at target rates.
Current and Future Work
The successful scale-up demonstrated through the first two milestones of TP7 set the conditions
to allow the commencement of bulk sample production.
TP7 continues with the production of a bulk sample commencing in December 2025. By mutual
agreement, Greenvale and Monash have extended the duration of TP7 at no additional cost to
Greenvale. Bulk sample production is currently scheduled for nine working weeks, with a two
week pause planned for the Christmas/New Year break.
The current schedule will see bulk production completed in late February 2026, with options to
extend the program if additional bulk sample material is required.
The bulk sample will be produced using drill core from the Alpha Torbanite project as the source.
Sample intervals were pre-selected and chosen based on their lithologies, bulk densities and
seam thickness, in order to be representative of both the target seam and the Resource area.
Drill core had, historically, been cut and left in wrapped core trays within a cold storage facility,
in order to protect the integrity of the material, preventing oxidation and moisture ingress.
Sample collection involved extracting the pre-selected intervals from the core trays, double-
bagging them and packaging them within plastic, 20-litre buckets, which were then transported
to ALS Global, Brisbane, for preparatory work before the main test work begins at Monash. Refer
to Appendix 1 for sampling details. Further information is given in Appendix 2.
The Alpha Torbanite Project has an Inferred Mineral Resource Estimate of 27.7Mt (in-situ) refer
to Table 12
.
2
Refer to ASX Announcement 51% Increase In Alpha Resource Substantially Expands Project Scale and Potential released 13
November 2023
Greenvale Energy Limited ASX Release
Page | 4
Table 1 – MDL 330 Inferred Mineral Resource Estimate by Seam and Ply Unit
Seam/Ply
Area
(m2
)
Volume
(cu m)
Waste
Thickness
(m)
Waste Volume
(bcm)
Tonnes
(Air Dried)
Tonnes
(Dry)
Tonnes
(in-situ)
U 5,199,146 5,409,700 21 181,383,104 6,491,640 6,653,931 6,437,543
L1 9,056,464 10,548,503 16 142,970,480 12,995,530 13,291,114 12,869,174
LT 6,774,137 3,635,190 0 157,694 4,301,324 4,325,876 4,289,524
L2 8,684,433 3,465,159 0 41,993 4,267,732 4,366,100 4,192,842
Total 28,056,227 28,637,021 27,789,083
Following the production of a bulk sample, bitumen processing specialist Technix will conduct
final product processing and will support Greenvale in independent product certification
process.
Product certification remains focused on achieving the C-170 specification. Other product
specifications and/or products may be investigated at a later stage.
Authorised for release
This announcement has been approved for release by the Board of Directors.
For further information please contact
Alex Cheeseman Nicholas Read
CEO Read Corporate
E: admin@greenvaleenergy.com.au E: nicholas@readcorporate.com.au
M: +61(0)419 929 046
About Greenvale Energy Limited
Greenvale is an ASX-listed exploration company with a portfolio of projects that will support a sustainable,
low-carbon future. The Company has early-stage uranium exploration projects in the Northern Territory,
the Oasis advanced-exploration project in Queensland and the Alpha Torbanite and Millungera Basin
geothermal projects in Queensland. The Company believes the best way to create long-term shareholder
value is by investing in exploration, to make discoveries and grow its resource-base.
Competent Person Statement
The information in this announcement, as it relates to exploration results, interpretations and conclusions,
is based on information reviewed by Mr Mark Biggs, who is an independent technical adviser to Greenvale
Energy Ltd and is a Member of the Australasian Institute of Mining and Metallurgy (AusIMM, #10788). Mr
Biggs is a Director of ROM Resources Consultant to the Company, and has sufficient experience that is
relevant to the style of mineralisation and type of deposit under consideration, and to the overseeing of
activities being undertaken to qualify as a Competent Person (as defined in the JORC 2012 edition of the
“Australasian Code for Reporting of Mineral Resources and Ore Reserves”. Mt Biggs consents to the
inclusion of this information in the form and context in which it appears.
Forward Looking Statements
This announcement may contain certain forward-looking statements and projections. Such forward
looking statements/projections are estimates for discussion purposes only and should not be relied upon.
Forward looking statements/projections are inherently uncertain and may therefore differ materially from
Greenvale Energy Limited ASX Release
Page | 5
results ultimately achieved. The Company does not make any representations and provides no warranties
concerning the accuracy of the projections and disclaims any obligation to update or revise any forward-
looking statements/projects based on new information, future events or otherwise except to the extent
required by applicable laws. While the information contained in this report hasbeenprepared in good faith,
neither the Company nor any of its directors, officers, agents, employees or advisors give any
representation or warranty, express or implied, as to the fairness, accuracy, completeness or correctness
of the information, opinions and conclusions contained in this announcement.
Greenvale Energy Limited ASX Release
Page | 6
Appendix 1 – Sample Details
Note: all coordinates are provided in GDA2020, zone 55
Hole ID Sample ID Easting Northing RL
Total
Depth
(m)
Azimuth
(°)
Inclination
(°)
Depth
From
(m)
Depth
To (m)
Interval
(cm)
Seam
GM11C GM11C3 481332 7333200 447 45 0 -90 37.53 37.73 20 LT
GM12C GM12C5
+ C6
481867 7333226 440 33 0 -90
22.09 22.75 66
LT/L2
GM12C 25.07 25.30 23
GM13C GM13C5 482325 7333171 445 25 0 -90 17.47 17.74 27 LT
GM57C GM57C3 482346 7332917 443 37.7 0 -90 24.72 25.22 50 LT
GM72C GM72C3
483103 7331906 446 42.7 0 -90
36.00 36.08 8 LT
GM72C GM72C4 36.08 36.21 13 LT
GM73C GM73C3
483605 7331921 461 49.05 0 -90
39.40 39.60 20 LT
GM73C GM73C4 39.60 39.75 15 LT
GM78C GM78C3 482041 7333418 445 27 0 -90 18.37 18.71 34 LT
GM80C GM80C4
482545 7333400 452 25 0 -90
16.43 16.49 6 LT
GM80C GM80C5 16.49 16.93 44 LT
GM81C GM81C3 482840 7333389 465 37 0 -90 26.92 27.56 64 LT
Total 390
Greenvale Energy Limited ASX Release
Page | 7
Appendix 2 - JORC Code, 2012 Edition – Table 1 Report
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (e.g. cut channels, random chips, or
specific specialised industry standard measurement tools appropriate
to the mineralsunder investigation, such as down holegamma sondes,
or handheld XRF instruments, etc). These examples should not be
taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity
and the appropriate calibration of any measurement tools or systems
used.
• Aspects of the determination of mineralisation that are Material to the
Public Report.
• In cases where ‘industry standard’ work has been done this would be
relatively simple (e.g. ‘reverse circulation drilling was used to obtain 1
m samples from which 3 kg was pulverised to produce a 30 g charge
for fire assay’). In other cases, more explanation may be required, such
as where there is coarse gold that has inherent sampling problems.
Unusual commodities or mineralisation types (e.g. submarine
nodules) may warrant disclosure of detailed information.
Samples for metallurgical testing (Test Program 7) were selected from 2023
exploration drilling, specifically HQ core as outlined in Appendix 1 (Table A1-1).
Details of the drilling program been provided in previous ASX releases in October
2023 and May 2025.
Standard drilling and core techniques were employed in generally shallow holes
drilled vertically.
Drilling
techniques
• Drill type (e.g. core, reverse circulation, open-hole hammer, rotary air
blast, auger, Bangka, sonic, etc) and details (e.g. core diameter, triple
or standard tube, depth of diamond tails, face-sampling bit or other
type, whether core is oriented and if so, by what method, etc).
Standard RAB and diamond HQ coring rigs were utilised.
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries
and results assessed.
• Measures taken to maximise sample recovery and ensure
representative nature of the samples.
• Whether a relationship exists between sample recovery and grade and
whether sample bias may have occurred due to preferential loss/gain
of fine/coarse material.
All core selected from testing was from boreholes with core recovery >90%.
Logging • Whether core and chip samples have been geologically and
geotechnically logged to a levelof detail to support appropriate Mineral
Detailed logging was not undertaken at the site but later after sample delivery to the
Greenvale Energy Limited ASX Release
Page | 8
Criteria JORC Code explanation Commentary
Resource estimation, mining studies and metallurgical studies.
• Whether logging is qualitative or quantitative in nature. Core (or
costean, channel, etc) photography.
• The total length and percentage of the relevant intersections logged.
lab. Logging was to the Coal Log V2 standard.
Whereas previously outcrop sampling of material has only been used for sighter
testing; with all Mineral Resource estimation, mining, and metallurgical studies to be
developed based evaluation of the core sample material.
Photographic records have been taken which shows each horizon sampled and the
weight of samples taken from each sample location has been recorded.
Sub-sampling
techniques and
sample
preparation
• If core, whether cut or sawn and whether quarter, half or all core taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and whether
sampled wet or dry.
• For all sample types, the nature, quality and appropriateness of the
sample preparation technique.
• Quality control procedures adopted for all sub-sampling stages to
maximise representivity of samples.
• Measures taken to ensure that the sampling is representative of the in-
situ material collected, including for instance results for field
duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material
being sampled.
The bulk sample was taken in substantial quantities of about 20 kilograms and of
both torbanite and cannel coal portions of the 63mm core. Samples were held by
Stratum and Subsampling for this exercise was undertaken by Stratum Laboratories.
Splits of approximately 400 grams were cut from subsamples obtained from Stratum
splits of the subcrop samples. Smaller samples were used in the program to
facilitate subsequent processing in the laboratory.
The splits were pulverised to sub 200 microns undertaken immediately prior to the
tests being conducted.
Subsamples were cut and placed under nitrogen and forwarded to Melbourne for the
test program at the Melbourne University.
Quality of assay
data and
laboratory tests
• The nature, quality and appropriateness of the assaying and laboratory
procedures used and whether the technique is considered partial or
total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc,
the parameters used in determining the analysis including instrument
make and model, reading times, calibrations factors applied and their
derivation, etc.
• Nature of quality control procedures adopted (e.g. standards, blanks,
duplicates, external laboratory checks) and whether acceptable levels
of accuracy (i.e. lack of bias) and precision have been established.
The subsamples had been held in refrigeration below zero in sealed bags.
Post pulverization the samples held under nitrogen overpressure until used.
A range of tests were conducted on the carrier oil and the sample types to ensure the
program could be meaningfully executed. Subsequent tests were then undertaken
to a standard set of procedures. In all 19 tests were conducted to establish the set
of 12 test result sets.
Laboratory tests were conducted based on standard analytical techniques such as
TGA, Proximate and Ultimate.
Verification of
sampling and
assaying
• The verification of significant intersections by either independent or
alternative company personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data
verification, data storage (physical and electronic) protocols.
The samples derived from the core have been observed by multiple personnel
including Engineers, Geologists and Greenvale employees have been involved in the
sample acquisition.
Greenvale Energy Limited ASX Release
Page | 9
Criteria JORC Code explanation Commentary
• Discuss any adjustment to assay data.
Location of data
points
• Accuracy and quality of surveys used to locate drill holes (collar and
down-hole surveys), trenches, mine workings and other locations used
in Mineral Resource estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
The samples taken are described in Table A1-1 in Appendix 1. Coordinate system
MGA55 GDA94 datum is expected to be accurate to +/- 0.30m.
Data spacing
and distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the
degree of geological and grade continuity appropriate for the Mineral
Resource and Ore Reserveestimation procedure(s) andclassifications
applied.
• Whether sample compositing has been applied.
The boreholes that the test sample was made up from have an average hole-to-hole
spacing of 745m, although this set is only a sub-set of the total hole database.
The base sample for testing this time was borecore from various depths, whereas
the initial, early metallurgical testing was essentially from a surface costean bulk
sample (50Kg) which would have had different characteristics to the less-weathered
core.
Orientation of
data in relation
to geological
structure
• Whether the orientation of sampling achieves unbiased sampling of
possible structures and the extent to which this is known, considering
the deposit type.
• If the relationship between the drilling orientation and the orientation
of key mineralised structures is considered to have introduced a
sampling bias, this should be assessed and reported if material.
Not relevant for this discussion of metallurgical testing. The deposit strikes at 300
degrees with gentle dips to the south and southwest. The intersecting boreholes
were planned as vertical.
Sample security • The measures taken to ensure sample security. Samples have been stored in dedicated freezers from the time the sample was
acquired and after sample preparation.
Chain of custody was managed by ALS, and later, Greenvale Energy.
Samples were transported in sealed bags, from ALS Brisbane to Monash University
in Melbourne.
Audits or
reviews
• The results of any audits or reviews of sampling techniques and data. No audits or reviews have been conducted.
Greenvale Energy Limited ASX Release
Page | 10
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria JORC Code explanation Commentary
Mineral
tenement and
land tenure
status
• Type, reference name/number, location and ownership including
agreements or material issues with third parties such as joint ventures,
partnerships, overriding royalties, native title interests, historical sites,
wilderness or national park and environmental settings.
• The security of the tenure held at the time of reporting along with any
known impediments to obtaining a licence to operate in the area.
MDL 330 is held by Alpha Resources Pty Ltd, a subsidiary of Greenvale Energy
Limited. MDL 330 was first granted on 1 February 2002. An application for a renewal
for an additional 5-year term was submitted in July 2021 and approved in July 2022.
The current 5-year term expires on 31 January 2027.
MDL 330 covers an area of 1,904.5 Ha.
Exploration
done by other
parties
• Acknowledgment and appraisal of exploration by other parties. Historically there has been exploration carried out over 85 years since the 1940’s.
The various titles have been held by Alpha Resources since 2002.
Table A2-1 lists the various explorers:
Geology • Deposit type, geological setting and style of mineralisation. The Alpha deposit lies within the axis of the Glen Avon Syncline, a southwest
plunging fold structure that occurs on the eastern flank of the Galilee Basin.
The deposit is part of the Permian Colinlea Sandstone, which contains 150 m of
cross-bedded sandstones with minor conglomerate, coal, siltstones, and
Greenvale Energy Limited ASX Release
Page | 11
Criteria JORC Code explanation Commentary
mudstones.
The Geology of the deposit consists of an Upper and Lower seam of cannel coal with
a torbanite lens present in the Lower seam.
The Colinlea Sandstone is thought to be a lower delta plain deposit with the coal
deposited in swamps and shallow lakes in this near shore environment. The
torbanite is thought to have been deposited from algae in a lacustrine environment
when water entering the system held little sediment or organic material.
Drill hole
Information
• A summary of all information material to the understanding of the
exploration results including a tabulation of the following information
for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in
metres) of the drill hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
• If the exclusion of this information is justified on the basis that the
information is not Material and this exclusion does not detract from the
understanding of the report, the Competent Person should clearly
explain why this is the case.
See Table A1-1 in Appendix 1, which includes all relevant new drill hole information
and seam intercepts.
All Greenvale and IMC exploration holes have been either traditional theodolite or
DGPS surveyed with stated accuracies of 0.1m in X & Y and 0.2m in Z.
Top of coal depths are accurate to 0.1m and interpreted from chip logs / core logging
and downhole geophysics, where carried out.
Where available verticality was loaded, and the holes were modelled accounting for
any inclination. An alternative model was generated treating all holes as vertical.
Data
aggregation
methods
• In reporting Exploration Results, weighting averaging techniques,
maximum and/or minimum grade truncations (e.g. cutting of high
grades) and cut-off grades are usually Material and should be stated.
• Where aggregate intercepts incorporate short lengths of high-grade
results and longer lengths of low-grade results, the procedure used for
such aggregation should be stated and some typical examples of such
aggregations should be shown in detail.
• The assumptions used for any reporting of metal equivalent values
should be clearly stated.
Torbanite and cannel coal horizons were modelled separately and not aggregated.
Relationship
between
mineralisation
widths and
• These relationships are particularly important in the reporting of
Exploration Results.
• If the geometry of the mineralisation with respect to the drill hole angle
is known, its nature should be reported.
• If it is not known and only the down hole lengths are reported, there
All drill holes were drilled at 90° to the surface and although some verticality logs are
available, the deposit was modelled where holes are assumed to be vertical.
Downhole verticality survey is available for all drill holes.
Greenvale Energy Limited ASX Release
Page | 12
Criteria JORC Code explanation Commentary
intercept
lengths
should be a clear statement to this effect (e.g. ‘down hole length, true
width not known’).
Seam intercepts are recorded on a downhole basis.
Downhole geophysical logs were used to confirm the seam intercepts and
thicknesses.
As the deposit is gently dipping and drill holes are generally shallow, the downhole
seam thickness will approximate the true thickness of the coal.
Diagrams • Appropriate maps and sections (with scales) and tabulations of
intercepts should be included for any significant discovery being
reported These should include but not be limited to a plan view of drill
hole collar locations and appropriate sectional views.
All appropriate diagrams have been released in preceding ASX Releases in March
2023 and May 2025
Balanced
reporting
• Where comprehensive reporting of all Exploration Results is not
practicable, representative reporting of both low and high grades
and/or widths should be practiced to avoid misleading reporting of
Exploration Results.
All available data for the Torbanite area has been collated and reported.
This release contains all relevant information.
Other
substantive
exploration data
• Other exploration data, if meaningful and material, should be reported
including (but not limited to): geological observations; geophysical
survey results; geochemical survey results; bulk samples – size and
method of treatment; metallurgical test results; bulk density,
groundwater, geotechnical and rock characteristics; potential
deleterious or contaminating substances.
GEOLOGY
The updated interpretation is predominantly based on the 2023 and 2021 drilling
results.
Limited historical drill hole information was used to supplement the 2021 and 2023
drilling and support the continuity of the Upper and Lower seams outside the bounds
of the MDL area.
METALLURGY
Supported by a base lube oil free or additives and then jointly subjected to pressure
and one temperature under a hydrogen atmosphere with varying amounts of an
industry standard catalyst. The program focussed on three sub-samples of cannel
coal. The same procedure was applied.
The results showed that the cannel coal sample weight loss continues to increase at
progressively higher temperatures, 365C, compared with the first test campaign at
348C and with a different catalyst at increasing catalyst concentration.
Cannel coal weight loss increased from about 22% (increased from 19% without
toluene wash) to about 39% based on tests including an additional wash of the
resultant solids in toluene to remove adhered asphaltenes.
Greenvale Energy Limited ASX Release
Page | 13
Criteria JORC Code explanation Commentary
Weight loss due to gas evolution remains low.
The results focused on achieving higher reactor temperatures using the outcrop
samples as in previous programs.
The results for Cannel Coal and Torbanite and respective blends demonstrate a
continued improvement at higher temperature such that the conversions rates of
52%, 63, and 67wt% respectively with no added catalyst on an as received basis,
which converted to 67%, 66% and 56wt% on the addition of 2wt% catalyst all at
400oC.
All tests showed conversion to Asphaltenes and Pre-Asphaltenes of over 10 wt%.
TGA tests have been conducted on the resultant solids post reaction and solvent
extraction. Some hydrocarbon volatiles remain, and so future programs will
investigate this further.
Further work • The nature and scale of planned further work (e.g. tests for lateral
extensions or depth extensions or large-scale step-out drilling).
• Diagrams clearly highlighting the areas of possible extensions,
including the main geological interpretations and future drilling areas,
provided this information is not commercially sensitive.
GEOLOGY
The current geological model will be used for any future work. It is currently not
known whether any further surface or sub-surface samples will be required for
metallurgical testing.
METALLURGY
The ongoing test program at Monash University will derive a large sample suitable for
downstream processing and ultimately seeking to achieve independent product
certification. Optimal conditions to produce such a bulk sample have been
identified, successful scaling of those conditions achieved, and the program
continues to determine if a bulk sample can be produced in a commercially viable
manner.