Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
31 October 2023
SEPTEMBER 2023 QUARTERLY ACTIVITIES REPORT
GREENVALE CLOSES-IN ON PIVOTAL MILESTONES AT
ALPHA TORBANITE PROJECT WITH TEST PROGRAM FOUR
COMMENCING AND RESOURCE DRILLING COMPLETED
Highlights
Alpha Torbanite Project, QLD (100%-owned):
•
Second phase of resource upgrade drilling completed on-site at Alpha, comprising 20 HQ
core holes for a combined 1,053.5m.
•
Resource model upgrade underway and due for delivery midway through the December
Quarter.
•
Commencement of liquefaction Test Program Four, with the completion of several initial
test runs by PROCOM, Licella and Monash University.
•
Samples sent for investigation and potential product identification at Technix’s New
Zealand-based bitumen laboratory.
Geothermal Project, QLD (100%-owned)
•
Initial Feasibility Study completed by CeraPhi Energy on the potential for power generation
at Longreach in Queensland
Georgina Basin IOCG Project, NT (20%-owned):
•
ExoSphere Ambient Noise Tomography (ANT) Survey underway to delineate structural
features and identify zones of potential IOCG alteration to assist with drill targeting.
Corporate:
•
High-potential growth and diversification opportunity in high-grade helium and hydrogen
secured subsequent to Quarter-end, with the proposed acquisition of a 75% interest in
the EP 145 Permit in the Amadeus Basin in Central Australia.
•
Greenvale maintains a substantial shareholding in Astute Metals NL., together with an
investment in the Georgina Basin, which includes a 2% net smelter royalty.
•
$0.465 million R&D Tax Incentive Rebate received for the 2022 financial year.
Greenvale Energy Ltd I ABN 54 000 743 555
Level 5/Suite 6 189 Kent Street SYDNEY NSW 2000
t:+61 2 8046 2792 | e: admin@greenvaleenergy.com.au | www.greenvaleenergy.com.au
Overview
During the September Quarter, Greenvale Energy Limited (ASX: GRV) made substantial
progress with its extensive work program at the Company’s flagship 100%-owned Alpha
Torbanite Project in Queensland. The program is focused on the delivery of the Project’s
maiden Preliminary Feasibility Study, due in Q1 2024. The current work program comprises
two components – the fourth stage of the laboratory-based liquefaction testing and the fieldbased second phase of resource drilling, designed to increase the size and confidence levels
in the Alpha Mineral Resource.
The quarter saw both the commencement of the final stage of liquefaction test work and the
completion of the second phase of drilling on-site at Alpha. The drill program, which comprised
20 HQ core holes for a combined 1,053.5m of drilling, was completed in late September, as
reported to the market on 2 October 2023. Final assays, interpretations and modelling are still
in progress and will be reported to the market in the December Quarter. The updated resource
modelling is expected to build on the previously reported 18.6Mt JORC Mineral Resource
Estimate (refer to ASX announcement, 10 March 2022).
The final stage of the liquefaction test work is progressing well and is currently on time for
delivery in line with the Company’s expectations. During the quarter, the Company’s technical
partners, PROCOM, Licella Holdings Ltd and Monash University all commenced test runs of
their respective liquefaction programs.
Licella completed the first of three supercritical scoping tests with the resultant samples sent
for external analysis at Petrolab in Melbourne. Monash University completed important
calibration work of their PARR reactor, under guidance from PROCOM. And PROCOM
completed several sample runs for analysis by Greenvale’s bitumen product advisors, New
Zealand-based Technix.
The completion of the second phase of drilling and the commencement of the final stages of
the liquefaction program are important steps towards the delivery of the Alpha PFS.
Management anticipates that a steady flow of news and updates from Alpha will be delivered
in the coming quarter as the work program gathers momentum.
During the quarter, the Company reviewed potential acquisition opportunities with a view to
diversifying its asset portfolio in sectors that complement its strategic focus on the Alpha
Torbanite Project. As a result of this, the Company acquired a 75% interest in the EP 145
Permit in the Amadeus Basin in Central Australia from Mosman Oil and Gas Limited. Full
particulars of the acquisition were announced on 17th October 2023.
The Company also continued to hold its investment in Astute Metals NL ("Astute Metals”).
During the quarter, the Company’s shareholding was diluted from 13.69% at the start of the
quarter to 11.21%. The Company retains a 20% interest in the Georgina Basin IOCG Project,
together with a 2% net smelter royalty. Astute Metals, which owns 80% of the Georgina
Project, progressed exploration activities during the quarter. To date, Greenvale has not been
required to fund any exploration activity.
Finally, during the quarter, the Company received a $0.465 million R&D Tax Incentive Rebate
for the 2022 financial year. The rebate further enhances the Company’s already strong
balance sheet position while also recognising the novel and cutting-edge work it is undertaking
to ensure that Greenvale becomes Australia’s only sustainable end-to-end producer of
bituminous products to feed growing domestic infrastructure needs.
GREENVALE
ENERGY
LIMITED
2
Projects
Alpha Project, Queensland
Background
The Alpha Torbanite Project is located approximately 50km south of the town of Alpha in
Central Queensland. The Alpha torbanite deposit consists of two seams, an upper seam of
mostly lower-grade mineralisation with an average thickness of 1.12m and a lower seam
containing lenses of torbanite up to 1.9m thick. The Project has been subject to extensive
exploration and laboratory testing since its initial discovery in 1939.
During 2019, SRK Consulting Pty Ltd (“SRK”) was engaged to reassess the Project’s
commercialisation strategy. SRK’s report set out a potential new development strategy based
on the production of a diversified suite of value-added products. SRK noted that, in contrast
with typical oil shale deposits, the Alpha torbanite deposit is exceptionally high-grade,
containing up to 650 litres of hydrocarbons per tonne of torbanite, and can produce high-value
bitumen, light crude oil and activated carbon.
The upper and lower bituminous shales also produce similar products, albeit at lower yields of
110-140 litres per tonne. Additionally, the torbanite and bituminous shales can deliver highquality value-added products through appropriate investment in processing infrastructure.
SRK was engaged to undertake a staged work program to assist in evaluating the project's
commercial viability.
Activities during the September Quarter
Liquefaction Test Program Four commenced during the quarter and is proceeding in line
with expectations. On 23 August 2023, the Company announced a work program
comprising three distinct assessments run by Monash University (Monash), Licella Holdings
Ltd (‘Licella’) and PROCOM/Technix.
Licella has been engaged to undertake a scoping study at batch level to better define the
yield and structure of products, under PROCOM direction, utilising variations of supercritical
water processing conditions that could potentially simplify the processing of the Alpha
torbanite deposit. Licella (refer to ASX release 5th October 2023) completed the first supercritical water test run during the quarter. This has provided Petrolab with samples from the
reaction tests for analysis. Petrolab’s work is continuing, but the initial results from the first
test run are expected to be provided in the December 2023 Quarter.
Monash University's ongoing work program involves verifying prior results using core
samples, conducting tests with both oil and supercritical water as carriers, and producing a
one-litre bulk sample for final analysis. They are also performing a full suite of tests on the
16 original core samples, providing periodic updates to Greenvale, and will deliver
comprehensive reports upon completion. This extensive program, currently in progress,
builds on positive results from earlier tests, establishing a processing pathway crucial for
the Alpha Project and the eventual Pre-Feasibility Study (PFS).
Monash has completed calibration of their PARR reactor and commenced its first test run.
The results of this initial test run will be released as soon as they are available. Future test
runs will provide further validity and context, noting that calibration of the Parr Reactor
equipment is a crucial step in the liquefaction test procedure and ensures that future testing
will be completed in a timely manner.
GREENVALE
ENERGY
LIMITED
3
PROCOM have continued their diligent work and have produced the first bulk samples (fivelitres) for independent assessment by Technix, Greenvale’s bituminous product advisor.
The bulk sample is currently in transit to New Zealand with Technix’s findings to be relayed
to the Company’s technical team as they become available. It is not anticipated that this
first sample will produce the final decided product suite; instead it is hoped that it will be
used by Technix to better understand the unique properties of the Alpha deposit.
The Company also expects that results from the recently completed Alpha Phase Two
drilling will also be made available in the December Quarter. As reported on 2 October 2023,
the Company completed Phase Two drilling at Alpha during the quarter with initial results
expected to increase both the size and confidence of the current 18.6Mt resource.
The core drilling program comprised a total of 20 HQ core holes for a combined 1,053.5m
of drilling. The program saw the acquisition of 16 cores targeting the Upper & Lower Seams
and four cores targeting just the Lower Seam. All core hole locations have been
geophysically logged with wireline tools providing down-hole gamma, density and verticality
surveys, with assays nearing completion. Respected mining consultants, SRK Consulting,
are completing the updated resource modelling. Management is confident that the resulting
resource estimate will further enhance the potential commercial viability of the Project.
Next Steps
With regard to upcoming works, the plan involves conducting further tests using the
PROCOM Parr Reactor, using a blend of torbanite and cannelite to produce more bulk
samples. This work is intended to build on current progress and prepare further samples for
analysis at Technix’s New Zealand bitumen laboratory.
Additionally, once more data from Test Program Four (Monash & Licella) becomes
available, the simulation work to estimate emissions and overall balances will continue. The
ongoing work of Licella and Monash is critical to the emissions estimations, as the
simulations rely on yield and quality assumptions from the liquefaction programs.
The projected emissions profile of the processing pathway will enable the modelling
required to form the basis for the Project’s renewable and offsetting strategy.
Lastly, the finalisation of the foundation for a large pilot plant targeting Licella's SPP is in
progress. This will enable the demonstration of key process flow elements and provide
larger samples for bitumen manufacturing testing.
GREENVALE
ENERGY
LIMITED
4
Geothermal Project, Queensland
Background
Greenvale and its wholly-owned subsidiary, Alpha Resources, is the 100% owner of a number
of exploration licences in north Queensland targeting geothermal energy projects. Geothermal
energy is the heat produced deep in the earth's core. Geothermal energy is regarded as a
clean, renewable resource that can be harnessed for use as heat and electricity.
Activities during the September Quarter
As announced on 11 May 2023, Greenvale launched a desktop Feasibility Study of the
Company’s Longreach (QLD) EPM, assessing the suitability of the area as a potential pilot
plant location for a small-scale geothermal power station.
During the Quarter, the Geothermal Feasibility Study, conducted in collaboration with
CeraPhi Energy ("CeraPhi"), was completed, with the Company reporting the findings to the
market subsequent to quarter-end on 4 October 2023.
The study was conducted by CeraPhi, who were engaged to assess the area’s geothermal
potential and evaluate the likely effectiveness of their CeraPhiWellTM down-hole heat
exchanger technology.
The study's outcomes are encouraging, revealing the capacity of the CeraPhiWell™
technology to provide the requisite heat for powering a 4.95MWe plant in the Longreach
region. However, Ceraphi has concluded that geothermal exploration below 3,000m depth
is unlikely to be economical at a small scale.
In light of this, Greenvale will now focus on the Millungera Basin geothermal potential, which
has target depths of 2.5-3kms and large-scale regional power requirements. CeraPhi
remains steadfast in its optimism about the potential of the CeraPhiWell technology within
the Australian landscape, underscoring its adaptability and applicability.
The Feasibility Study confirmed the presence of an ample geothermal heat source in the
Longreach area and validated the viability of utilising the down-well closed-loop technology
for supporting a power station. However, due to insufficient opportunities for commercial
off-take and the lack of any heavy industry in the area, building a pilot plant in Longreach
was deemed sub-economic.
Next Steps
The focus of Greenvale’s geothermal program will now shift to the Millungera Basin, with
the Company also exploring avenues for reducing well costs, including potential rig
acquisition tailored to the project's needs.
The Company is also undertaking a thorough sub-surface assessment to identify drilling
risks and define subterranean stratigraphy more accurately.
GREENVALE
ENERGY
LIMITED
5
Georgina Basin IOCG Project, Northern Territory
Background
The Georgina Basin IOCG Project is owned by Knox Resources Pty Ltd (Knox), a company
which is 20%-owned by Greenvale. As part of its ownership of Knox, the Company is required
to contribute to the funding of its share of Knox’s future costs. Greenvale is entitled to a 2%
net smelter royalty (Royalty) for all Iron Oxide Copper Gold (IOCG) product exploited in the
future from the existing tenements owned by Knox.
Activities during the September Quarter
EL33375 Gravity Surveying
During the quarter, Knox commenced a gravity surveying across its highly prospective Central
Georgina Project tenement EL33375. The prospect-scale gravity survey is designed to
enhance gravity data resolution between recent drilling and previous National Drilling Initiative
drill-holes, as well as to align with coverage of the forthcoming Ambient Noise Tomography
(ANT) survey, which is one of two recently awarded Exploration Grants as part of the NT
Government’s Resourcing the Territory Geophysics and Drilling Collaborations Program.
Figure 1. Georgina IOCG Project and general gravity survey location.
Previous prospect-scale gravity surveying in this area, conducted by Greenvale as the previous
operator, resulted in the generation of three distinct IOCG targets, namely Banks, Leichhardt
West and Leichhardt East – all of which were drill tested in mid-late 2022.
The drill-holes intersected variably altered metasedimentary rocks, with assay results revealing
significant anomalism in copper, as well as uranium, silver and bismuth, which are known to
be associated with IOCG deposits.
GREENVALE
ENERGY
LIMITED
6
Figure 2. Existing prospect-scale gravity imagery, planned in-fill gravity stations
and Ambient Noise Tomography (ANT) survey outline.
The gravity stations are strategically located to improve the resolution of gravity data between
the existing datapoints, extended both to the north and south to incorporate drill-holes
NDIBK05 and NDIBK10 which were drilled by Minex CRC as part of the inaugural National
Drilling Initiative (NDI) drill program in 2020.
This drill program was the culmination of many years of investment and work by Geoscience
Australia and the NT Geological Survey, and resulted in confirmation that the East Tennant
region is highly prospective for IOCG deposits. By extending coverage to the NDI holes, this
will allow Knox to incorporate drilling data from those locations into the broader interpretation
for the region, leveraging the additional information into future interpretations.
The results of the survey and the ANT survey will be fundamental to guiding future work and
are expected to result in the identification of further drill targets in this highly prospective region.
The 548-station survey is due to be completed within a week.
Ranken Geophysical Surveying
During the quarter, Knox completed geophysical surveying at its Ranken Project area, in the
eastern part of its Georgina IOCG Project in the Northern Territory. The commencement of the
survey followed the recent release of Geoscience Australia’s National Mineral Potential for
Sediment-Hosted Zinc-Lead Mineral Systems in Australia mapping and extended abstract,
which highlights the Ranken Project area as being highly prospective for sediment-hosted base
metal mineralisation.
GREENVALE
ENERGY
LIMITED
7
The geophysical surveying, which was co-funded by the NT Government Resourcing the
Territory initiative, was designed to identify gravity (density) anomalies and establish depth to
prospective basement rocks.
The Ranken Project area is located to the east of the main part of the Georgina Project, close
to the NT-Queensland border. Possessing different interpreted basement geology, the Ranken
area is interpreted to cover host-rocks prospective for sediment-hosted base metal deposits
such as the world-class Century and Mount Isa deposits.
Data from the two-part survey, which comprised both gravity and HVSR Passive Seismic
surveying, is being processed to allow for interpretation over the coming months.
This interpretation will be used to guide the final design and collar location for the Company’s
first drill-hole at the Ranken Project, which was also the subject of a recently awarded
Exploration Grant as part of Round 16 of the NT Government’s Resourcing the Territory
Geophysics and Drilling Collaborations Program.
In mid-March 2023, there was a release of new nationwide mineral potential maps from
Geoscience Australia, which assesses for the prospectivity of four types of sediment-hosted
base metal mineral systems across Australia.
Astute previously highlighted the prospectivity of the Ranken Project area (EL32285 and
EL32286 in Figure 10) for Century-style and Mount Isa-style sediment hosted deposits, and
confirmation of this assessment by Geoscience Australia further strengthens the rationale
underpinning the geophysical gravity and HVSR passive seismic surveys. The mapping,
shown in Figure 10, predicts mineral potential via a ‘heat map’ style whereby the hotter the
colour the more prospective the area.
The study assessed for potential for clastic-dominated siliciclastic carbonate, clasticdominated siliciclastic mafic, Mississippi Valley-type and Irish type sediment hosted deposits,
using a Mineral Systems approach which considers the source of metals and fluids, energy
sources and fluid flow drivers, fluid flow pathways and depositional mechanisms.
The Ranken area is most prospective for the clastic-dominated sub-type of deposits, with major
deposits including Hilton-George Fisher (24.2Mt contained Zn and 12.4Mt contained Pb),
Century (13.7Mt contained Zn and 2.0Mt contained Pb) and Mount Isa Zn-Pb (10.5Mt
contained Zn and 9.0Mt contained Pb)1. Each of these deposits also contain significant silver.
GREENVALE
ENERGY
LIMITED
8
Figure 3. Georgina IOCG Project tenements and Geoscience Australia
mineral potential ‘heat map’, with hotter colours more prospective – noting
the Ranken Project tenements EL32285 and EL32286 to the far east of the project.
Northern Territory Government Co-funding Grants
During the quarter, Knox was awarded two co-funding grants through the Geophysics and
Drilling Collaborations (GDC) program, which is administered by the Northern Territory
Geological Survey (NTGS). The Company took part in the Round 16 Geophysics and Drilling
Collaborations program, with the following successful applications having been made:
•
Grant 1 is for $100,000 toward an Ambient Noise Tomography (ANT) survey on the
Central tenement area EL33375, where recent drilling intersected copper and uranium
mineralisation; and
•
Grant 2 is for $161,106 (representing 50% of eligible drilling costs) towards a 700m deep
drill hole at the Company’s Ranken area
GREENVALE
ENERGY
LIMITED
9
Corporate Activities
Acquisitions
During the quarter, the Company reviewed a number of acquisition opportunities with a view
to diversifying its asset portfolio in areas that complement its strategic focus on the Alpha
Torbanite Project. As a result, the Company entered into an agreement to acquire a 75%
interest in the EP 145 Permit in the Amadeus Basin from Mosman Oil and Gas Limited. Full
particulars of the acquisition were announced in the Company’s announcement released to
the ASX on 17 October 2023.
Investment in Astute
The Company continues to hold a substantial interest in Astute Metals NL (ASX: ASE) (11.21%
as at 30 September 2023). The Company’s shareholding decreased from 13.69% at the start
of the quarter due to dilution caused from various capital raising initiatives undertaken by
Astute.
Research and Development Grant
During the quarter, the Company received a $0.465 million R&D Tax Incentive Rebate for the
30 June 2022 financial year. This grant strengthened the Company’s balance sheet and
reflects the innovative work that is being undertaken for the development of the Alpha Torbanite
Project.
GREENVALE
ENERGY
LIMITED
10
ASX Additional Information
The Company provides the following information pursuant to ASX Listing Rule requirements:
1.
ASX Listing Rule 5.3.1:
Exploration and Evaluation Expenditure during the quarter was $1,118,300. Full details
of exploration activity during the September 2023 quarter are set out in this report.
Below is the breakdown of the expenditure incurred:
Table 1 Analysis of exploration expenditure for the September 2023 quarter
Property
Nature of expenses
Amount ($)
Alpha Project
Alpha Testwork
254,392
Drilling costs
570,081
Geology and geophysics
Mining administration and environmental
compliance cost
40,337
89,243
Rent and rates
43,883
Subtotal – Alpha Project
997,936
Mining administration and environmental
compliance cost
70,018
Feasibility study costs - Ceraphi Energy Ltd
50,346
Subtotal – Geothermal Project
120,364
Geothermal Project
Total Exploration costs
2.
1,118,300
ASX Listing Rule 5.3.2:
The Company confirms that there was no mine production and development activities
for the quarter.
GREENVALE
ENERGY
LIMITED
11
3.
ASX Listing Rule 5.3.5: Payment to related parties of the Company and their
associates during the quarter was $151,120 in cash.
The Company advises that this relates to remuneration of Directors only. Set out below
is the following additional information in relation to the Appendix 5B enclosed:
Table 2: Director’s remuneration for the September 2023 quarter
Name of Director
Nature of Payment
Amount ($)
Neil Biddle
Ongoing Director fees
33,300
Elias (Leo) Khouri
Ongoing Director fees
30,000
Mark Turner
Ongoing executive director renumeration
87,820
Total Director Remuneration
151,120
Tenements
In accordance with Listing Rule 5.3.3, Greenvale provides the following Information concerning its
exploration licences:
Tenement Details
Alpha Project, Queensland
Tenement
%age Ownership
MDL 330
100%
EPM 27718
100%
Owned by
Alpha Resources Pty Ltd
Alpha Resources Pty Ltd
Geothermal Project, Queensland
Tenement
%age Ownership
Of Applicant
EPM 28265
100%
EPM 28266
100%
EPM 28487
100%
EPM 28488
100%
EPM 28489
100%
EPG 2021
100%
EPG 2022
100%
EPG 2023
100%
EPG 2024
100%
EPG 2025
100%
EPG 2029
100%
GREENVALE
ENERGY
LIMITED
Status
Current to 31 January 2027
Current to 14 February 2026
Applicant
Status
Alpha Resources Pty Ltd
Alpha Resources Pty Ltd
Greenvale Energy Ltd
Greenvale Energy Ltd
Greenvale Energy Ltd
Alpha Resources Pty Ltd
Alpha Resources Pty Ltd
Greenvale Energy Ltd
Greenvale Energy Ltd
Greenvale Energy Ltd
Greenvale Energy Ltd
Withdrawn
Withdrawn
Surrendered
Surrendered
Withdrawn
Withdrawn
Withdrawn
Under Application
Under Application
Under Application
Under Application
12
Authorised for Release
This announcement and the accompanying Appendix 5B have been approved by the
Board for release.
Contact
For further details, contact:
Mark Turner, CEO, 0459 519 999
Media Inquiries:
Nicholas Read – Read Corporate
Nicholas@readcorporate.com.au
Mobile: 0419 929 046
GREENVALE
ENERGY
LIMITED
13
COMPETENT PERSON’S STATEMENT – ALPHA TORBANITE PROJECT:
The information in this report that relates to Exploration Results is based on
information compiled by David Cavanagh, a Competent Person who is a Member of
The Australasian Institute of Mining and Metallurgy AusIMM Member number 112318.
David Cavanagh is a full-time employee of Core Resources.
David Cavanagh has sufficient experience that is relevant to the style of mineralisation
and type of deposit under consideration and to the activity being undertaken to qualify
as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’.
David Cavanagh consents to the inclusion in the report of the matters based on his
information in the form and context in which it appears.
The Company confirms that it is not aware of any new information or data that
materially affects the information included in the Mineral Resource Estimate dated 9
March 2022 as announced to the ASX on that date and which is available at
www.greenvaleenergy.com.au. The Company confirms that in relation to the Alpha
Torbanite Project Mineral Resource Estimate, all material assumptions and technical
parameters underpinning the estimate continue to apply and have not materially
changed when referring to its resource announcement made on 9 March 2022.
COMPETENT PERSON’S STATEMENT – GREORGINA BASIN IOCG PROJECT:
The information in this report that relates to Exploration Results is based on
information compiled by Mr Matthew Healy, a Competent Person who is a Member of
The Australasian Institute of Mining and Metallurgy (AusIMM Member number
303597).
Mr Healy is a full-time employee of Astute Metals NL (formerly Astro Resources NL).
Mr Healy has sufficient experience that is relevant to the style of mineralisation and
type of deposit under consideration and to the activity being undertaken to qualify as
a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves’.
Mr Healy consents to the inclusion in the report of the matters based on his information
in the form and context in which it appears.
GREENVALE
ENERGY
LIMITED
14
Rule 5.5
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Greenvale Energy Ltd
ABN
Quarter ended (“current quarter”)
54 000 743 555
30 September 2023
Consolidated statement of cash flows
Current quarter
$A’000
1.
Cash flows from operating activities
1.1
Receipts from customers
1.2
Payments for
(a) exploration & evaluation
Year to date
(3 months)
$A’000
(18)
(18)
(404)
(404)
3
3
464
464
45
45
(1,118)
(1,118)
(b) development
(c) production
(d) staff costs
(e) administration and corporate costs
1.3
Dividends received (see note 3)
1.4
Interest received
1.5
Interest and other costs of finance paid
1.6
Income taxes paid
1.7
Government grants and tax incentives
1.8
Other (provide details if material)
1.9
Net cash from / (used in) operating
activities
2.
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
(e) investments
(f)
other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
Current quarter
$A’000
Year to date
(3 months)
$A’000
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
3
3
(1,115)
(1,115)
-
-
5,168
5,168
45
45
2.3
Cash flows from loans to other entities
2.4
Dividends received (see note 3)
2.5
Other (provide details if material)
2.6
Net cash from / (used in) investing
activities
3.
Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2
Proceeds from issue of convertible debt
securities
3.3
Proceeds from exercise of options
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
3.5
Proceeds from borrowings
3.6
Repayment of borrowings
3.7
Transaction costs related to loans and
borrowings
3.8
Dividends paid
3.9
Other (provide details if material)
3.10
Net cash from / (used in) financing
activities
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
4.3
Net cash from / (used in) investing activities
(item 2.6 above)
(1,115)
(1,115)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
-
-
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow repo
Share your feedback
Discover